Capital Projects

$16.6 Million Capital Project Approved by Voters May 17, 2016

 

Construction Bids Awarded February 6, 2018

  • HSE Library Addition and Reconstruction
    • Gut renovation
    • Addition
    • Incidental work in rooms above for connection to utilities and rooftop equipment
    • Construction June 2018-December 2018
  • High School East, Gowana, Acadia and Koda Roofing & Flooring Abatement
    • Roofing replacement/overlay
    • Flooring abatement and replacement
    • Construction June 2018-August 2018

 

 

    Anticipated Opening for Bid in March 2018

    • Stadium Press Box & LightingPicture of stadium rennovation
      • New press box and stadium lights
      • New transformer at High School West
      • Construction Spring/Summer 2018
    • District-Wide CO Detectors & Window Film
      • Carbon monoxide (CO) detectors
      • Impact resistant window film per New York State Education Department requirements
      • Construction Spring-Fall 2018
    • Elementary School Playgrounds
      • Playground upgrades
      • ADA (American Disabilities Act) enhancements
      • Construction Spring-Fall 2018 (some 2019 work)

     

    Anticipated May 2018 Submission to NYS Education Department for Approval

    • District-Wide Signage
      • Exterior wayfinding and field signs
      • Building/entry identifiers
      • Anticipated Construction Spring-Fall 2019 (if approved by NYSED by January 2019)
    • Five-Year Facilities Maintenance Plan Items
      • Asbestos Abatement
      • Ventilation
      • Code Upgrades
      • Irrigation
      • Anticipated Construction Spring-Fall 2019 (if approved by NYSED by January 2019)

     

     

     

    $22.2 Million Capital Project Approved by Voters December 5, 2017

      Design Phase 

      • Science Room Modernization at High School East
        • Modernizing 8 science and 4 prep rooms on the 2nd floor
        • Converting 4 art rooms into 3 modernized science and one prep room on the 1st floor
        • Anticipated Phased Construction – Dates TBD

       

       

      • HS Technology Wing ModernizationHigh School Map
        • Transforming existing Technology Classroom area into High School “STEAM (Science, Technology, Engineering, Art and Math) Center”
        • Art rooms incorporated into new STEAM Center
        • Anticipated Phased Construction – Dates TBD

       

      • HS East Kitchen/Cafeteria
        • Modernizing space to provide better flow and use
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval
      • Gowana, Acadia and Koda Cafeterias
        • Provide acoustical treatments to remediate excess
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval
      • Natural Gas Infrastructure
        • Provide natural gas infrastructure for future use in kitchens at High School West, Gowana, Acadia, Koda, Karigon/Orenda, Skano/Tesago, Okte and Chango
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval
      • Bus Garage & Maintenance Facility
        • Provide emergency generator for essential services
        • Replace existing bus lifts
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval
      • Parking
        • Replace existing asphalt at Koda and Acadia with new asphalt
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval
      • Upgrade electrical distribution
        • Karigon/Orenda, Skano/Tesago, Okte, Chango, Gowana, Acadia, Koda, HS West and HS East
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval
      • Security/Phone/Technology
        • Provide additional server space for disaster recovery
        • New VoIP phone system
        • Re-testing existing campus fiber and add new as required
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval

      Photo of Rte 146 Entrance

      • Traffic Flow Rt 146 Entrance Reconfiguration
        • Move School Road towards Middle School providing additional space for vehicles entering campus
        • Provide additional lane to stack vehicles leaving Elementary School area
        • Provide additional lane to stack vehicles leaving campus
        • Provide Campus Map pull off lane entering campus
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval

       

       

       

      • Traffic Flow Moe Road Entrance ReconfigurationPhoto of Moe Rd Entrance
        • Provide additional lane entering campus extending to tennis court allowing for turning lane into HSE
        • Extend additional lane leaving campus for vehicle stacking
        • Provide secondary access to student parking
        • Provide student drop-off single entry/exit
        • Provide new entry access to Faculty parking
        • Provide Campus Map pull off lane entering campus
        • Anticipated Construction Summer 2019 based on January 2019 SED Approval